Background
It is generally accepted by aircraft enthusiasts that the
Spitfire was one of the most beautiful aircraft ever built. This is largely due
to its flowing lines and gentle curves throughout.
From a restorers point of view, these same lines make it
a somewhat difficult to rebuild, and certain parts can be a nightmare to
reproduce with the usual equipment found in the average sheet metal workshop.
Further complicating matters is the fact that throughout
its development life, many of the various marks were achieved by taking an
existing mark of aircraft and adding or “tweaking” bits as an “interim fix” to
achieve an overall performance increase. However, in a few cases the designers
did start with a clean sheet of paper, and the process of modification started
again.
Spitfire restorations will really soak up the hours, with
a figure of 35,000 to 40,000 now becoming the generally accepted norm. Of
course this will vary with how the hours are actually counted, or accounted for
. i.e.
are the hours spent on parts sourcing and research included.
Mh603 has been around for quite a while, having been
started in the UK back in the 1980’s and subsequently sold to the USA, where
restoration work continued on and off for a few years. The aircraft was again put up for sale in
2009, and was purchased by Pay’s Air Service. At that stage it was essentially an (
outwardly ) completed fuselage and empennage, with the balance of the project
as a kit of individual parts and minor sub assemblies. The container arrived at
Scone aerodrome in late 2009, and restoration at scone commenced in March 2010.
One of the first tasks carried out was to perform a
detailed assessment of what was there, what needed further work, and what was
missing. Unfortunately, it was soon discovered that the aircraft was far from
complete, and a lot of effort was needed to be put in to sourcing the balance
of the parts.
Early on it was decided to restore the aircraft as
authentically as possible, and this includes the use of appropriate British
hardware. At some stage, a lot of American fasteners had been installed, and
these have been replaced with the correct items. The correct British “purple”
rivets will be used throughout, although these are now becoming quite hard to
come by, and can be expensive. In Spitfire rebuilds, rivets are generally
replaced as a matter of course, because in the factory, Supermarine drawings
gave the option of either the high- magnesium, or low- magnesium rivets as able
to be used, and after 70-odd years, there is really no way of knowing which
type was originally installed. Therefore the prudent course of action is to
replace all the rivets, regardless of how sound the joint still
appears.... and there are a LOT of
rivets.
Fuselage
The stub spars that the wings attach to ( also called
carry-through spars) were replaced with new items as a matter of course.
Also, we had become aware of murmurings among the
Spitfire community that the fuselage structure was out of alignment. This was
checked and it was discovered that the rear wing attach points were slightly
out, along with the stub spar position. This was rectified when the spars were
replaced, along with the fwd fuselage skins being renewed. The four main attach
points for the engine mount were also dismantled and inspected, with several
items replaced in the process.
The cockpit area is another area that has a few problems,
with the Right hand canopy rail not extending far enough forward, necessitating the
replacement of that rail and the adjacent skin.
Lastly , a couple of the fuselage frames had incorrect
profiles, and replacement frame sections have been sourced. A couple of aft
fuselage skins are also being replaced, to give a neater joint where the tail
unit attaches.
Over the 2012 Christmas period, the fuselage was
externally taken back to bare metal, corrosion protected with alodine and
repainted with epoxy primer. The
internal surface of the fuselage was rubbed back and repainted in silver (
aluminium ) colour. The exception being the immediate cockpit area, which is almost
always green. This was repainted with a slightly different shade, as matched to
a paint sample from the original aircraft.
A new instrument board has been made, as well as a new
cockpit ventilator system.
The seat and its mount/ adjuster mechanism is complete,
but need some minor cosmetic rectification before it is fit for use. A new leather seat back padding has been made
as per original configuration, even including some original kapok and horse
hair filling.
The fire baffle between the cockpit and fuel tank was
largely missing. The task of producing this assembly was placed in the capable
hands of Pioneer Aero Ltd, and the kit of parts for this unit is now largely
complete.
Canopy and windscreen.
Only the canopy Perspex bubble and a few minor sheet
metal parts arrived with the kit. The incredibly tricky canopy forward frame
has been reproduced ( plus a few spares ) and the remainder of the canopy items
are in the process of being sourced or made locally, including the latch and
jettison mechanism.
The windscreen assembly has been dismantled, assessed and
is currently being reassembled with new side panels being made in house. The
manufacture of the laminated glass
forward screen has been outsourced locally, and is due for installation shortly.
A rear vision mirror is still required.
Upon arrival the wings were essentially a largely
incomplete kit of parts, having originated from multiple sources.
One of the main concerns was that the spar booms were part of an early batch that had been made from material of insufficient strength. Fortunately, as the booms were not built into any structure, it was a relatively simple process to send them back to the UK to have them heat treated up to the required strength. They now have no flight limitations on them, and are installed in the leading edge assemblies.
The 2 wing leading edge assemblies ( also called D- boxes because of their cross
section) are now almost complete, with the skins being drilled off and trimmed
for the final time before being riveted on permanently.
We have been fortunate to be able to have the use of an
original set of leading edges, from which an assembly fixture was made. This
has enabled us to keep everything aligned during assembly, and ensure that the
correct washout is maintained. The spitfire has about 2-1/2 degrees of washout,
and with its elliptical wing, this is quite tricky to measure. The spar is
built flat and the angle that the ribs are attached to it progressively changes
along its span.
The D-box rebuild
is incredibly fiddly and time consuming, with a lot of double and triple
handling involved. In itself, it
actually consumes almost half the labour and materials cost of the total wing
rebuild, although at first glance this would not appear to be the case. The
trailing edge structure from the main spar aft is relatively straight forward
by comparison.
There is now a complete set of ribs on hand, with the
missing parts either made in-house or sourced elsewhere.
A complete set of wing flaps is now on hand, as are the
radiator fairings and flaps. The wing tips are complete, only requiring
cosmetic rectification in the leading edge area. The special attach hardware
for the tips are now on hand.
The ailerons, however, produced a problem which we
weren’t expecting. At first glance, they
appeared to be complete and ready to fit.
A quick assessment revealed that they were in fact the “short span”
type, as fitted to the MK8 and Mk14 aircraft, and therefore will need to be
lengthened by some 10 inches. To achieve this a new spar will have to be
installed, along with several new ribs and skins. Fortunately, these parts are
now sourced and on their way to us.
The wings will have the required modifications to allow
the use of “straight” axles, and it is envisaged that they will also be
modified to incorporate fuel tanks in the gun and ammo bays, as per the TR9
Spitfire.
Recently, we were able to acquire a very rare genuine
Spitfire bomb carrier mechanism. A pair of these will ultimately be fitted to
the wings of this aircraft, and the standard wing tank configuration will be
altered slightly to accommodate the internal wing structure required for these.
Airframe Assemblies Ltd in the UK is currently producing
a wing to fuselage kit for the aircraft, and it is envisaged this will be on
hand for when the wings are mated to the fuselage.
Empennage.
The tail portion of the fuselage is largely complete,
with the exception of some cosmetic rectification required. Missing minor
brackets and parts have now been sourced, with only the tailplane to fuselage
fairings to be made.
The 2 halves of the tail plane are complete, however the
special attach hardware still needs to be sourced. The elevator and rudder are
both structurally complete, and only need covering and finishing. This will be carried out nearer to completion
of the project.
Systems
A full set of flight control cables and attaching parts
is on hand, as is most of the mechanical system parts for the flight controls
The rudder control system has been completely dismantled,
NDT’d re-cadmium plated and
reassembled. The support structure for
the flight control components has been completely rectified or replaced as
necessary. In this area, a bit of “artistic license” had been previously used
with some replacement parts of incorrect configuration and spec being used. These areas have now been rectified by
the use of new correct items.
A complete set of oil and coolant pipes has been
completed and on hand, and work is now
underway on the associated brackets and connections.
Instruments and electrical.
On hand is a fibreglass replica of the original radio mast,
with a modern aerial for the emergency locater installed inside. An original
under wing IFF aerial has been sourced, and this will be used with the modern
VHF radio, maintaining a stock outward appearance. We are always on the lookout
for instruments and electrical items, as usually several items of one
particular unit are required before a serviceable ( airworthy) part can be
assembled.
Landing Gear
A complete set of landing gear components are on hand.
However, the outer cylinder for the right hand main gear is corroded, and a
replacement item is being sought. New
original tubes were found on site !, and original tyres have been sourced.
Complete NOS brake units are on hand too, as well as new drums, yet to be
fitted to the new wheels. New retraction ram assemblies currently being
manufactured by Supermarine Aero.
A set of blank panels for the cowls, and some of the
reinforcing structure arrived with the kit. The missing parts for the panels
themselves have now all been either made in-house, or sourced from overseas. A
complete kit of parts for the cowling support structure has now been sourced.
A new carburettor air box has been manufactured, as well
as a couple of spare items made for trading purposes.
Thanks for the update you have nicely covered this topic. keep it up
ReplyDeletePatented one to many RC based wrist band control